New site development for a new 400,000 square foot Logistics Center. Building pad was pre-graded prior to beginning work.

The 30 acre site required 26,000 cy of material to be excavated and placed on site (cut/fill) for pavement areas. Landscape areas required an additional 22,000 cy clean fill material and topsoil cover be placed over marker fabric. Scope also included 12,450 lineal feet of curb and gutter, 7,500 square feet of concrete sidewalk, 2,800 square yards of concrete dolly pads and 63,000 square yards of aggregate base and asphalt paving. The work required to complete this project included:

  • Grading
  • Stone Base
  • Concrete Curb and Gutter
  • Concrete Sidewalk
  • Concrete Dolly Pads
  • Asphalt Paving
  • Pavement Striping

Project Details

Client(s)

Glen Arm Building Company

Locations

Tradepoint Atlantic – Sparrows Point, MD